ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/17/2023 is T-9 business days until Go Live.
Federal holiday 5/29/2023
Current build info. Make sure you are testing with the most recent build.
Check in your profile settings in the app to be sure.
Platform | Build | Access | MobileToolbox |
---|---|---|---|
iOS | 1.5.0 (111) | Testflight | v1.5.2 |
Android | 0.28.36 (36) |
Current study info
*The QA study may crash on some Android devices because the schedule is quite large to accommodate many repeatable sessions. I have set up a short QA study that can be used for Android testing.
Study | Study ID | SynID | Data access team |
---|---|---|---|
ICAR - QA Project Twei2 | mtbwrj | ||
ICAR short study | vwrdjf | ||
Research Study (ICAR Pilot) | pgdvpj | ||
ICAR Validation | TBD | TBD | TBD |
Work item ID | Description | Status | Next steps | Who |
---|---|---|---|---|
After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done | Triage - deprioritized | This is expected behavior to spec for the 2nd administration of a CAT engine measure. Not required for pilot study. | NU to triage and prioritize this work according to researcher needs | |
duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannon | |
N/A | Receive and integrate new build from NU to resolve
| Resolved | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/15 | Keith, Nate, Shannon |
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | In progress | Issues found with caching and exit button activity | Sage QA, NU QA, NU researchers |
Data is failing validation due to use of reserved keyword $schema within the taskdata | Blocked | Agreed on plan for $schema and array-->object fixes. Aaron to make the changes and publish to github. | Aaron | |
Continue development work on pipeline | In Progress | Pending alignment on resolution schema type validation fails | Phil | |
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra |
N/A | Not started | Start this after study config is complete | Sonia | |
N/A | Resolved | confirmed .json--> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | |
Setup permissions so scoring code can run | Resolved | Test out as part of scoring code review | Larsson should now be able to run scoring code when ready | |
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new builds | Larsson |
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding. Expected completion 5/19 | Phil |
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson |
Exit activity on measures does not exit if user is delayed. iOS only | Resolve - unable to reproduce | New testflight build 111 was unable to reproduce issue. Resolving and will monitor for future. | Ann, Jasmine |
Open questions
Put it here, please don’t leave it in email and assume it is being tracked.
Question | Who is asking | Answer | Answered by |
---|---|---|---|
0 Comments