Daily status

Daily status

 

ICAR pilot study is expected to start June 1, 2023

ICAR validation study is expected to start September 1, 2023

 

T was reset to 6/12 for release to App stores to accommodate additional updates

Completion:

iOS and Android apps released to production on 6/12/2023

Platform

Build

Access

MobileToolbox

Platform

Build

Access

MobileToolbox

iOS

1.5.0 (116)

App Store - QR code

v1.5.6

Android

0.28.41

App Store - QR code

v1.5.9

 

Work item ID

Description

Status

Next steps

Who

Work item ID

Description

Status

Next steps

Who

DHP-926 - Getting issue details... STATUS

After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done

Triage - deprioritized

This is expected behavior to spec for the 2nd administration of a CAT engine measure. No changes required for pilot study.

NU to triage and prioritize this work according to researcher needs

DHP-923 - Getting issue details... STATUS

duplicate zip archives were being created on iOS

Resolved in iOS build 109

none

 

N/A

Receive and integrate new build from NU to resolve

  1. include $schema fix

  2. include array-->object fix

  3. include UX fixes

Resolved

Build is expected from NU by 9AM pacific on 5/19 or faster if possible. Cutoff day to receive final build is 5/23

Keith, Nate, Shannon

N/A

QA to check for completion, build integrity, raw .json arrival and structure in Synapse

Resolved

ongoing generation and evaluation raw .json

Sage QA, NU QA, NU researchers

ETL-440 - Getting issue details... STATUS

Data is failing validation due to use of reserved keyword $schema within the taskdata

Resolved

none

 

DHP-936 - Getting issue details... STATUS

New Android validation errors. jsonschema property is not being included in metadata.json

Resolved

none

 

DHP-935 - Getting issue details... STATUS

New validation errors. jsonschema property is not being included in metadata.json

Resolved

none

 

DHP-937 - Getting issue details... STATUS

Assessments not being marked as completed in Android

Resolved - blocked

This issue to be addressed as part of a future overhaul of data upload

 

DHP-940 - Getting issue details... STATUS

Android assessment data is missing a required property

Resolved

 

 

DHP-938 - Getting issue details... STATUS

Study schedule is locked and metadata is not updateable for the study. Only known resolution is to create a new study and pipeline

Resolved

none

 

Missing upload

Resolved - won’t fix

This is part of a larger architectural revamp of uploads that we will work through post-renewal. This state is NOT different than our current live clinical studies.

Shannon

ambiguous encoding of userinteractions

Resolved

QA in iOS build 115

Keith

Pause and ‘continue later’ restarts the 3DR activity from the beginning instead of last item

Resolved

addressed in build 114

Anyelo, Stephanie

Continue development work on pipeline

Resolved

Pipeline is working, only need to update and merge to complete. Validate Android validation errors with 5/24 builds.

Phil

IBCSPRT-174

Onboard pilot study to pipeline

Resolved

https://sagebionetworks.jira.com/l/cp/jnuvVAAi

 

Add permissions for the new study that was created to pick up metadata updates to the assessments

Resolved

none

 

Setup permissions so scoring code can run on Pilot study

Resolved

none

Larsson should now be able to run scoring code when ready for QA study

Setup permissions so scoring code can run on the short QA study for Android data

Resolved

none

Larsson should now be able to run scoring code when ready for QA study

N/A

Final scoring requirements

Resolved

none. confirmed .json--> parquet will use schema validation only

 

Setup permissions so scoring code can run on ICAR QA study

Resolved

Test out as part of scoring code review

Larsson should now be able to run scoring code when ready for QA study

TBD

Update scoring code

Resolved

Pending parquet availability

Larsson

IBCSPRT-174

Deploy pipeline for pilot study

Resolved

none

 

TBD

Parquet and scores UAT

Resolved

Parquet is available for both iOS and Android.

Aaron, Hugh, Larsson

Exit activity on measures does not exit if user is delayed. iOS only

Resolved - unable to reproduce

New testflight build 111 was unable to reproduce issue. Resolving and will monitor for future.

 

Raw JSON not available in last 2 builds for Android

Resolved

verify is within measure code. When confirmed a new build will be required. Unknown if iOS is also affected

Anyelo, Aaron, Keith

Update measure time estimates

Resolved

Ann/Sonia to update

Ann/Sonia

 

 

Open questions

Put it here, please don’t leave it in email and assume it is being tracked.

Question

Who is asking

Answer

Answered by

Question

Who is asking

Answer

Answered by

 

 

 

 

 

 

 

 

Related content

Scoring requirements from NU
Scoring requirements from NU
More like this
MyCogMobile requirements
MyCogMobile requirements
Read with this
Daily status - MyCogMobile release
Daily status - MyCogMobile release
More like this
Mobile Toolbox Monthly Status Summaries
Mobile Toolbox Monthly Status Summaries
Read with this
Mobile Toolbox Status Summary - June/July 2023
Mobile Toolbox Status Summary - June/July 2023
More like this
Mobile Toolbox Status Summary - April/May 2023
Mobile Toolbox Status Summary - April/May 2023
Read with this