ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/12/2023 is T-10 business days until Go Live.
Federal holiday 5/29/2023
Current build info. Make sure you are testing with the most recent build.
Check in your profile settings in the app to be sure.
Platform | Build | Access | MobileToolbox |
---|---|---|---|
iOS | 1.5.0 (110) | Testflight | v1.5.2 |
Android | 0.28.36 (36) |
Current study info
*The QA study may crash on some Android devices because the schedule is quite large to accommodate many repeatable sessions. If this happens to you let me know. If it is a systemic issue I will setup another study for Android.
Study | Study ID | SynID | Data access team |
---|---|---|---|
ICAR - QA Project Twei2 | mtbwrj | ||
ICAR Pilot | TBD | TBD | TBD |
ICAR Validation | TBD | TBD | TBD |
Work item ID | Description | Status | Next steps | Who |
---|---|---|---|---|
After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done | Triage | Try to repro in the non-persistent QA study. Consider setting up a study that runs each measure twice sequentially. | Sage and NU QA | |
duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannon | |
N/A | Receive and integrate new build from NU to resolve
| Resolved | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/15 | Keith, Nate, Shannon |
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | Not started | Initial round completed. Next round pending new builds. Expect QA from 5/15 - 5/19 minimum | Sage QA, NU QA, NU researchers |
Continue development work on pipeline | Blocked | waiting for new builds and new data generation | Phil | |
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra |
N/A | Not started | Start this after study config is complete | Sonia | |
N/A | Resolved | confirmed .json--> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | |
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new builds | Larsson |
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding | Phil |
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson |
Exit activity on measures does not exit if user is delayed. iOS only | In Progress | Ann/Jasmine to verify os version in staging app and in testflight | Ann, Jasmine |
Open questions
Put it here, please don’t leave it in email and assume it is being tracked.
Question | Who is asking | Answer | Answered by |
---|---|---|---|
Add Comment