11/1/21
What went well:
What could go better: Less firefighting. More of a controlled roadmap with actual requirements and designs and planning.
There is difficulty in having sidebar conversations for dev purposes across different teams
Action:
Communication Planning and documentation:
For requirements: We should add the ability to document who required the item and why.
Is this in the project plan
Breakdown what is in the grant prior to and during submission to evaluate feasibility
And after grant is approved, we should breakdown the actual stories with high level features
Need to have a grant breakdown planning process with roadmap and resource allocation
Need to have open conversations with researchers for the requirements:
Access to Larrson and his time.
Utilize mPower requriements for adding to MTB assessments. to leverage options for study bursts.
10/18/21
Study Bursts are not as defined as should be. Feels okay about design and server frameworks, but open questions are expected.
Dual Account signup and Enrollment work to be completed. Additionally working on documentation
Android - Investigate Mpower assessment integration, Data Tracking documentation and feasibility relating to things like medications etc.
iOS- Investigate data tracking feasibility for MTB
Investigate
Exporter - continuation.
10/4/21
QA feedback:
Worried that so few QA bugs were logged. It seems like most of the bugs were filed by internal (Design) and not with the QA team.
Needs more explicit requirements for testing and the test plan.
Need more devices to test with. Erin will approve request.
Need to find devices - Nate states he had a few in the drawer.
8/23/21
Sprint Schedule is WIP - Final Draft stages. This is not “locked” and will only be used as a guideline for remaining work.
What went well:
Release Documentation process is going well.
Meetings are more productive as we are scheduling the priorities and able to reduce some of the noise
Decisions are getting easier to make more quickly and not requiring re-work.
What could go better:
8/9/21 -
Feedback - post sage week - none at this time
Action Item
Design Feature cutoff -Ann to work on for future planning
New stories added?
7/26/21
Sage week required carry over of most sprint items.
7/12/21
New Priority Process with planning for Mobile Toolbox work.
-Reviewed full list of features for MTB October release
Follow up meeting to be scheduled to work through T shirt sizing stories
-Need to do full breakdown for each epic with correct stories included.
Ann to include link to document once finalized.
6/28/21
What went well:
Jack still ramping up and its getting easier
Productivity is up
What could go better:
Temp is up - this is bad
Passive Data repository is a large story. Should try to estimate prior to starting a task. Still working through the tasks to get it ready
Estimating uploads without Erin is difficult
Action Items :
Reduced velocity due to the Monday holiday and potential vacation time - Expected to impact total output
6/14/21
App launched - have been doing fixes and new builds from NU
...