MyCogMobile study is expected to start no later than mid-July on July 17, 2023. There will be no parquet or scores generated for this study, only raw .json in Bridge Raw Data folder.

To hit this date, THE CUTOFF DATE FOR NU TO SUBMIT ADDITIONAL BUILDS IS 7/11/2023. This allows time for a final QA and time for App Store review and publication. Any builds that are needed after 7/11 will cause a day-to-day slip.

Build Info:

Make sure you are using the current build for testing

Platform

Build

Access

MobileToolbox

iOS

1.5.1 (116) - this build does not upload data. Wait for the next build before doing QA.119)

TestFlight https://testflight.apple.com/join/zQCIGILz

Turn off auto-update setting on your account within the TestFlight App.

v1.6.03

Study

Study ID

SynID

Data access team

MyCogMobile QA study 1 Project AQ4p

zqgrmk

MyCogMobile QA study 1 Project AQ4p5 - syn51713466 - Files (synapse.org)

MyCogMobile QA study 1 Access Team AQ4p5 (synapse.org)

TBD MyCogMobile live study

TBD

TBD

TBD

...

Work item ID

Description

Status

Next steps

Who

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyDHP-962

multiple taskdata files generated with same name is causing archive and upload to fail

Open

Review PR provided by Shannon and send new build

KeithQA

Generate QA data and validate that raw .json is arriving in Synapse

Anyelo/Andrey/Sonia

Open questions

Put it here, please don’t leave it in email and assume it is being tracked.

...