ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/17/2023 is T-9 business days until Go Live.
...
Work item ID | Description | Status | Next steps | Who | |||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done | Triage - deprioritized | This is expected behavior to spec for the 2nd administration of a CAT engine measure. Not No changes required for pilot study. | NU to triage and prioritize this work according to researcher needs | |||||||||
| duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannonnone | |||||||||
N/A | Receive and integrate new build from NU to resolve
| In Progress | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/1519 or faster if possible. Cutoff day to receive final build is 5/23 | Keith, Nate, Shannon | |||||||||
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | In progressIssues | found with caching and exit button activityGeneration and evaluation of Android raw .json | Sage QA, NU QA, NU researchers | |||||||||
| Data is failing validation due to use of reserved keyword $schema within the taskdata | Blocked | Agreed on plan for $schema and array-->object fixes. Aaron to make the changes and publish to github. | Aaron | |||||||||
| Continue development work on pipeline | In Progress | Pending alignment on resolution schema type validation fails | Phil | |||||||||
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra | Resolved | none | |||||||
N/A | Not started | Start this after study config is completeIn progress | Sonia | ||||||||||
N/A | Resolved | none. confirmed .json--> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | ||||||||||
| Setup permissions so scoring code can run | Resolved | Test out as part of scoring code review | Larsson should now be able to run scoring code when ready for QA study | |||||||||
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new buildsparquet availability | Larsson | |||||||||
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding. Expected completion 5/19 | Phil | |||||||||
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson | |||||||||
| Exit activity on measures does not exit if user is delayed. iOS only | Resolve - unable to reproduce | New testflight build 111 was unable to reproduce issue. Resolving and will monitor for future. | Ann, Jasmine |
...