ICAR pilot study is expected to start June 1, 2023

ICAR validation study is expected to start September 1, 2023

Today 5/17/2023 is T-9 business days until Go Live.

...

Work item ID

Description

Status

Next steps

Who

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyDHP-926

After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done

Triage - deprioritized

This is expected behavior to spec for the 2nd administration of a CAT engine measure. Not No changes required for pilot study.

NU to triage and prioritize this work according to researcher needs

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyDHP-923

duplicate zip archives were being created on iOS

Resolved in iOS build 109

QA on new 5/12 build

Sonia, Shannonnone

N/A

Receive and integrate new build from NU to resolve

  1. 4 distinct $id for schemas

  2. fix to 3D measure steps

  3. any other fixes

Resolved
  1. include $schema fix

  2. include array-->object fix

  3. include UX fixes

In Progress

Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/1519 or faster if possible. Cutoff day to receive final build is 5/23

Keith, Nate, Shannon

N/A

QA to check for completion, build integrity, raw .json arrival and structure in Synapse

In progressIssues

found with caching and exit button activityGeneration and evaluation of Android raw .json

Sage QA, NU QA, NU researchers

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyETL-440

Data is failing validation due to use of reserved keyword $schema within the taskdata

Blocked

Agreed on plan for $schema and array-->object fixes. Aaron to make the changes and publish to github.

Aaron

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyETL-426

Continue development work on pipeline

In Progress

Pending alignment on resolution schema type validation fails

Phil

N/A

Setup ICAR pilot study config

In Progress

NU to complete study setup by 5/17.

Stephanie, Lizz, Zahra

Resolved

none

N/A

Onboard pilot study to pipeline

Not started

Start this after study config is completeIn progress

https://sagebionetworks.jira.com/l/cp/jnuvVAAi

Sonia

N/A

Final scoring requirements

Resolved

none. confirmed .json--> parquet will use schema validation only

Lizz, Aaron, Hugh - signoff needed from Larsson

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyDHP-928

Setup permissions so scoring code can run

Resolved

Test out as part of scoring code review

Larsson should now be able to run scoring code when ready for QA study

TBD

Update scoring code

Not started

Pending final reqs. Test out with QA study after new buildsparquet availability

Larsson

TBD

Deploy pipeline for pilot study

Not started

Pending completion of dev work and onboarding. Expected completion 5/19

Phil

TBD

Parquet and scores UAT

Not started

Pending pipeline and scoring code completion

Aaron, Hugh, Larsson

Jira Legacy
serverSystem JIRA
serverIdba6fb084-9827-3160-8067-8ac7470f78b2
keyDHP-927

Exit activity on measures does not exit if user is delayed. iOS only

Resolve - unable to reproduce

New testflight build 111 was unable to reproduce issue. Resolving and will monitor for future.

Ann, Jasmine

...