ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/
...
16/2023 is T-
...
10 business days until Go Live.
Federal holiday 5/29/2023
...
Work item ID | Description | Status | Next steps | Who | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done | TriageOpen | Try to repro in the non-persistent QA study. Consider setting up a study that runs each measure twice sequentially. | Sage and NU QARepro’d in QA study that behavior appears 2nd time through the measure. Another report that it occurs on teh first time through even after deleting and reinstalling app. | Shannon has done a prelim investigation. Assigned to Keith for resolution | ||||||||||||
| duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannon | |||||||||||||
N/A | Receive and integrate new build from NU to resolve
| Resolved | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/15 | Keith, Nate, Shannon | |||||||||||||
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | Not started | Initial round completed. Next round pending new builds. Expect QA from 5/15 - 5/19 minimumIn progress | Issues found with caching and exit button activity | Sage QA, NU QA, NU researchers | ||||||||||||
| Continue development work on pipeline | In Progress | Pending alignment on resolution schema type validation fails
| Data is failing validation due to use of reserved keyword $schema within the taskdata | Blocked | Need alignment between Keith, Shannon, Aaron and Phil on the appropriate resolution. | Shannon has proposed a solution, need feedback from Keith and Aaron on implementation plan. | ||||||||||
| Continue development work on pipeline | In Progress | Pending alignment on resolution schema type validation fails | Phil | |||||||||||||
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra | |||||||||||||
N/A | Not started | Start this after study config is complete | Sonia | ||||||||||||||
N/A | Resolved | confirmed .json--> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | ||||||||||||||
| Setup permissions so scoring code can run | Resolved | Test out as part of scoring code review | Larsson should now be able to run scoring code when ready | |||||||||||||
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new builds | Larsson | |||||||||||||
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding. Expected completion 5/19 | Phil | |||||||||||||
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson | |||||||||||||
| Exit activity on measures does not exit if user is delayed. iOS only | In Progress | Ann/Jasmine to verify os version in staging app and in testflight | Ann, Jasmine |
...