ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/15/2023 is T-11 business days until Go Live.
...
Work item ID | Description | Status | Next steps | Who | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| After doing the practice puzzle, user is immediately shown the “Exit Activity” screen indicating that assessment is done | Triage | Try to repro in the non-persistent QA study. Consider setting up a study that runs each measure twice sequentially. | Sage and NU QA | ||||||||||||||||
| duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannon | ||||||||||||||||
N/A | Receive and integrate new build from NU to resolve
| Resolved | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/15 | Keith, Nate, Shannon | ||||||||||||||||
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | Not started | Initial round completed. Next round pending new builds. Expect QA from 5/15 - 5/19 minimum | Sage QA, NU QA, NU researchers | ||||||||||||||||
| Continue development work on pipeline | In Progress | Pending alignment on resolution schema type validation fails
| Aaron, Shannon, Keith to agree on fix and work with Phil | ||||||||||||||||
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra | ||||||||||||||||
N/A | Not started | Start this after study config is complete | Sonia | |||||||||||||||||
N/A | Resolved | confirmed .json--> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | |||||||||||||||||
| Setup permissions so scoring code can run | Resolved | Test out as part of scoring code review | Larsson should now be able to run scoring code when ready | ||||||||||||||||
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new builds | Larsson | ||||||||||||||||
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding | Phil | ||||||||||||||||
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson | ||||||||||||||||
| Exit activity on measures does not exit if user is delayed. iOS only | In Progress | Ann/Jasmine to verify os version in staging app and in testflight | Ann, Jasmine |
...