ICAR pilot study is expected to start June 1, 2023
ICAR validation study is expected to start September 1, 2023
Today 5/11/2023 is T-11 business days until Go Live.
...
Work item ID | Description | Status | Next steps | Who | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
| duplicate zip archives were being created on iOS | Resolved in iOS build 109 | QA on new 5/12 build | Sonia, Shannon | ||||||||
N/A | Receive and integrate new build from NU to resolve
| In progress | Build is expected from NU by 9AM pacific on 5/12. Sage will create integrated build on 5/12. Data generation can begin against new test builds on Monday 5/15 | Keith, Nate, Shannon | ||||||||
N/A | QA to check for completion, build integrity, raw .json arrival and structure in Synapse | Not started | Initial round completed. Next round pending new builds. Expect QA from 5/15 - 5/19 minimum | Sage QA, NU QA, NU researchers | ||||||||
| Continue development work on pipeline | Blocked | waiting for new builds | Phil | ||||||||
N/A | Setup ICAR pilot study config | In Progress | NU to complete study setup by 5/17. | Stephanie, Lizz, Zahra | ||||||||
N/A | Not started | Start this after study config is complete | Sonia | |||||||||
N/A | In progress | Larsson needs to know where in the schema these fields appear. NU team please update the reqs doc Resolved | confirmed .json-- >parquet from NU otherwise will default to current rules and behaviors> parquet will use schema validation only | Lizz, Aaron, Hugh - signoff needed from Larsson | ||||||||
TBD | Update scoring code | Not started | Pending final reqs. Test out with QA study after new builds | Larsson | ||||||||
TBD | Deploy pipeline for pilot study | Not started | Pending completion of dev work and onboarding | Phil | ||||||||
TBD | Parquet and scores UAT | Not started | Pending pipeline and scoring code completion | Aaron, Hugh, Larsson |
...